Mass excavation was completed over the University break.  The remaining dirt in the holding bay in the UC lot is slated to be used for infill at footings. Concrete pours are continuing this week, despite the weather with a wall pour scheduled for Monday, January 23rd at the G level.  The plaza elevator pit base and walls will be poured this week and next. This elevator is located in the northeast corner of Harney plaza close to UC.  All foundations for the building are scheduled to be complete in the next two weeks.  The next suspended slab pour is currently scheduled for February 8, 2012.